Okay, so the Y and T connectors for the vents are ready to be connected to, but I haven't framed anything in the bathroom, so I won't be able to finish the venting until later. Here's when I took my trusty rag and shoved it into the opening to prevent noxious gas from escaping into the sterile environment of my workspace.

The image to the right show my 3/4" pipe headed into my bathroom. A plumber would not give me any points for prettiness, but it worked so I'm movin' on.
So today we turn our attention to fresh water plumbing. Basically, I just needed to run lines to the future location of the toilet, shower, and tub. Actually, I just need to bring the lines close to that spot and rough it in. The existing piping for the sinks sinks is about 6" off from where it will need to be, but I'm going to put a bend in that when I get to that portion of our show. I capped off the water line for the toilet during demo so now I need to turn off the house water main and start cutting and sweating. That's when I started thinking about water pressure. My plan calls for a shower with water jets, a normal shower head and an overhead, 4-head "rain" system by Kohler. The tub is decent size and we've got two sinks. I'm a little worried about water pressure. Back to the internet.
The recommendations from Kohler were for 3/4" pipe instead of the standard 1/2". More flow. Makes sense. Course, that means that the primary hot and cold lines coming into my bath are inadequate. I traced the lines back and in my basement above the pool table there actually are 3/4" lines that split off and become 1/2". I could just extend that into my bathroom. Course, I wasn't really planning on this change either.
Okay, after a trip to HD, I was back and prepared to open a line in my basement that was directly over my pool table. Subsequently, this was VERY dangerious work. I cut, put in my connector and began to sweat the pipe. It didn't work. This took many attempts, many cuts and lots of swearing. Once back at HD, I asked about this and the problem is that the line that still connects to fresh water is cold and likely still wet. Apparently an old trick is to shove a piece of bread up in the pipe. The bread absorbs the water and eventually disolves. This allows a dry opportunity to begin the sweating. This was still tough and because it wasn't completely dry, the weld didn't hold and it leaked. I had to break it apart, sand, cut...more leaks.. wash, rinse repeat.
The image to the right show my 3/4" pipe headed into my bathroom. A plumber would not give me any points for prettiness, but it worked so I'm movin' on.
Each time I want to do something with the water, I have to turn the house main off. This is one of those old round valves that is already showing signs of moisture around it. So I say a little prayer to the gods to keep the valve from blowing off while I'm turning it off and on. To avoid this, I thought it would be a good idea to install shut off valves for just the bathroom. For whatever reason, I couldn't make this happen. I bet I shoved an entire baguette up that pipe and it still wouldn't sweat. Just kept breaking off in my hand. Now each time I fail I need to break this thing off, sand and in one case, go to HD and buy a new valve. It was getting late and Jen would likely like to have some water in the house before too long. I went back to HD to find some kind of miracle. I found it in the form of an expensive connector called a SharkBite. Simply put, they just connect to copper pipes like tinker toys. You can put them on and take them off all day, and they are approved for behind-wall use. I would never use anything else expect they are expensive. The only bad thing here was that I spent most of my day overcoming this problem and buying more pipe before I came to this solution.
The water is back on, nothing appears to be leaking, the pool table is intact and Jen doesn't know how close we came to a flooded basement. I'm golden.