Friday, August 21, 2009

Time to test the water

The plumbing on the shower and the tub are done. I just need to put the valves in on the sink and plumb the toilet. The fauctes for the sink are going to be coming out of the wall. They look pretty cool in the pciture but I've never done this before. My big problem is how deep in the wall to mount them see, they have to stick out a specific amount so that the pretty part of the faucet is flush with the wall. My issue is that my wall includes drywall, tile and an indeterminate amount of mortar.

I've been avoiding this for some time but today is the day. I measured some 12 times including two eyeball / sanity checks. They have to be centered in a space that isn't complete yet so it's a bit tricky. They also have to be the right level above a sink that isn't there yet. The actual installation isn't that hard. I put a 2x4 in the wall and screwed the bracket that holds the valve up to it. Then remeasured just for fun to make sure. Good thing I did too because after all that I was off by 1/2 inch. I took it down, and moved it then remeasured. Then determined I was right the first time and moved it back. Jen decided it was lunch time so I quickly agreed to stop.


More sweating of pipe with trusty torch. By the way, I didn't factor any copper pipe into my budget. Copper pipe is expensive. A little while later the valves to the sink were connected to fresh water pipes.

The last bit was taking fresh water to where the toilet was going to be. This toilet calls for water to come out of the wall and not the floor. Means a few more bends and stuff but wasn't my biggest problem today. I plumbed that and capped it off so that I have a pipe sticking out of the wall waiting for my toilet..one day.

Okay, now to test the water. The tub plumbing is completely done and I put plugs into the outlets of all of my shower fixtures (body sprays, overhead, etc). The valves on the sink will contain the water there, if they're turned off. It's kind of hard to tell. And I capped off the toilet water by welding a cap. So, in theory, if the water were turned on, no water would come out.
I asked Jen to get into the crawl space and showed her the master on/off valves. She can also hear me through the floor. This was pretty nerve racking stuff to be honest. I've had my welds fail before on other projects. I yelled down to Jen "okay, turn the cold on just a wee bit." Folks, it's a bit terrifing when you hear all that water charging the system and you know pressure is now behind all the work done by an unlicensed plumber. We did the hot and eventually worked up to full strength. I don't know what to tell you. It worked. No leaks. Well, except one.
Remember me telling you about the compressions fittings for the tub faucet? Yeah, a very slow leak appeared. I tightened, thentightened some more, then tightened too much and bent the pipe and the leak got worse. Back to McGukins. Tried again. Failed. Back to McGukins. This time buying far more than I needed. Tried again. I was up to three leaks at one point. These are very small leaks that take a while to even see. But they have to be fixed. This was pretty frustrating stuff. But after some 5 attempts including rebending and installing the tubing, it finally worked. I hate compression fittings.

So the water is on. The sinks, toilet, tub and shower pipes have pressurized water in them and I'm not screaming down at Jen "Turn it off! For the love of god turn it off!!!!" I was so surprised by this I sat in my shower chair for about 1/2 hour just staring at the plumbing.


Thursday, August 20, 2009

The tub doesn't fit

So the jetted tub has been in my garage for a while. I created the deck using the template they provided. Kind of a big oval. So I created the frame for this thing and then put the deck down. Then just for fun I measured the oval against the tub. Yeah, it doesn't fit. No seriously. The opening accomodates the rim of the tub but not the two motors, pipes electrical thing a ma bobs that are all permanently mounted to the tub. So, I took the deck off and called Mike. I needed someone to help me carry it into the house.


I had measured the sliding glass door and the new doorway to the bathroom to make sure the tub would fit. But now that Mike was on his way, I panicked and measued again only to find out that now the tub wouldn't fit through my newly framed door. I quickly set to work tearing down the jack studs. By the time Mike got here I was done and we carried the tub in with little problem. Turns out, I forgot that I had planned to turn the tub sideways and didn't have to tear apart the door. This by the way is only one of a hundred similar mistakes that I've omitted mostly because I've blocked them from my mind.
So the tub's lowered in and I decided to start on plumbing. The access is there so why put the deck on when I don't need it yet. The drain part came first. Nothing terribly interesting to tell you there. I did test it with a bucket of water. This is a good time to mention that your drain should be installed with plumbers putty. Quick fix. I think even the pros make that mistake.
Fresh water. The lines in the crawl space went in as expected. I put in extra valves so that I could shut off the tub, independent of the whole bathroom. Once I ran the lines up to the tub valves then I encountered trouble. The hot and cold runs to a waterfall faucet. They use compression fittings and 1/4 copper tubing. This had to be bent. Suffice to say that a compression fitting and tube must be in pristine condition to keep from leaking. Well, you bend this and that doesn't happen. This took two trips to McGukins because I was optimistic that I could get it right on the next try.

So now I have a tub sitting in an open frame. It's mostly level, and the plumbing seems to be holding. It looks pretty cool.


(To the right you can see more of the shower plumbing and my favorite chair where I sit for long periods wondering how much trouble I've gotten myself into).

Wednesday, August 19, 2009

I'm really unqualified to be doing this

So I've got my shower framed in. What it needs is some plumbing. Actually, so does the toilet, the tub and the sinks but the shower is what I'm most afraid of. My dad always said, when it comes to home improvement, face your fear. Actually, that may be been Tim "the tool man" Taylor. Anyway, I was more or less excited to get this going so today I started plumbing.


First I made sure Jen was on ready alert with the fire extinguisher. Next I returned to the scary crawl space and ran a line from down there up through the floor. There was some drilling involved but by now I had purchased a dill bit set and was well equipped. The tools I keep buying by the way, yeah, they're not in the budget. Jen's been pretty understanding so far. Might be the medication.


Okay, so during this time there were some four trips to HD, Lowes, McGukins and HD again. Mostly because when the shower fixtures come, they come with the valves and the valves don't have installtion instructions. They just figure that a certified plumber is going to be doing this work, not a cheap bastard with a MAPP tortch.


I plumbed up to the main temperature control valve. Sounds cool eh? So we'll one day have a shower that has separate temperature and volume (on to off) valves. I put that on and then realized I better brace it pretty quickly because it weighs some 20 pounds (or thereabouts).


There are three sections from here. One goes off the the right to an on/off valve and then on to the normal shower head. The other goes to another on/off and then to an over head shower head called "Rain." It's four shower heads all combined in one. I've never seen it working. Just looks awesome. The last are two body spays that are mounted on the wall. All of these are flat. That is, they don't stick out from the wall. They're called water tiles. Kohler makes them. They're cool. I'm hoping I don't break them.


I'm sweating all of this 3/4 pipe to brass fittings. The trick here is to get it hot enough to melt the solder but not melt the wee plastic pieces inside the expensive valves. My problem in the past also included welding one angle but through heating it up, weakening the weld I just made. Basically, I worked quickly and used a wet towel to cool the previous weld. I'd like to say I never made a mistake, but that just wouldn't be my style. But through carefully measuring, cutting, sweating, breaking the welds, cleaning measuring again, cutting and sweating again, I got it done.


Now, here's the fun part. I can't check the welds. If I turn water on, well water might come out and go all over my unfinished shower. There are plugs that I can buy to screw into the valves and then turn it on. I may need to do that. Anyway, this is done. Until I find out it leaks. Then I won't be all that done.

Let's poke holes in the roof

If you're tyring to figure out why I did this before finishing that, I have no answer for you. Basically I've found that when I reach a problem, I avoid it and ponder it while doing something else. So today I jumped over to putting in the ceiling fan. It was a nice day so why not poke a hole in my roof.

I read up on this a bit and with the proper installation and lot of tar caulk (not the exact name), I should expect 20 years of leakless venting. Course, the "my luck" factor combats that bringing it down to about 7.

So basically, I found a lovely spot in the middle of the bathroom and poked a hole in the ceiling. Then I went into the attic (an extremely hot, insullation filled space with about 3 feet of headroom). Found the hole I poked and installed the fan there. Then eyeballed where the vent in the roof would go and did basically the same thing. Then I climbed up on the roof and found the small hole I just drilled. Now all I had to do was saw out a larger hole for the vent. Cutting a hole in your roof is not a natural act. I remembered my insurance agent. I remembered the nice lady who gave us the big loan on the house. Then I steeled my nerves and went for it. Now get this, it rained tonight. Yup, I didn't get much sleep.

Tuesday, August 18, 2009

Let's start framing




Okay, so I started framing. Basically there's a few things to do. The shower is the most important so that I can finish up the plumbing. After that there is a half-wall to hide the toilet and and the platform for the tub. Oh and I have to frame a decent window and then frame a door. There wasn't a door into the bathroom before.






The shower is going to be a steam shower. Besides buying a steam engine, and running the dedicated electrical line and plumbing for that, I found out that this also means a few other things. First off, no natural stone. Water vapor will make it through into the walls and do bad things. Second, there seems to be a debate about whether to slope the ceiling. This is very important. With a flat ceiling, condensation will collect rapidly and drip furiously down upon you as you're trying to relax. Lastly, the entire shower (walls and ceiling) must have a vapor barrier.


I been measuring out my shower for weeks and think it has the right dimentions. Not too small or too large. So, the framing began. Two indespensible tools in this category. First, the miter saw. I love it. it's so amazing. Second is the nail gun I purchased for the construction of the closet. I can't tell you how fast the work goes. Now all I have to do is make is square, which I more or less did. I'm telling you, it's not as easy as it should be. I measured, marked, had my speed square handy and it was still a bit off.

Another note on framing a shower. Use 2x6's on the wet wall. You can squeeze it all in using 2x4's but if you can avoid that headache, do so.
Next I tackled the door. Here you get to deal with terms like king studs and jack studs. Basically this is pretty straight forward. Squareness is again important. I'm getting better at it.
Framing the window was pretty scary. That involves poking a hole into a perfectly good wall. You know, one that leads to the outside where snow and wolves are. My window was sitting in the garage so I felt pretty solid about how big I had to make this. I tried to be careful so that I would not destroy the outside panneling. It didn't work out and they don't make the exact kind of panneling anymore..of course. So, I'm hoping that gobs and gobs of paint will hide that fact.
The tub. Yeah, this was hard. Everything must be level, square and perfectly plumb. I had exact dimentions for the tub as provided by Jason tubs. The deck, was created out of 3/4 plywood using my jig saw. I have a crappy little saw. This took a while.
So the above took a few days all told. I'm wrapping it up here for reader convenience. I sure wish I had a jaccuzzi to relax in.